Key Takeaways
- For bare-space stalls, organisers usually need stall drawings, contractor details, a power order and sometimes structural details before build-up.
- The exhibitor manual is the rulebook: it lists deadlines, height limits, material rules, power charges, deposits and build-up and dismantling timings.
- Late submissions often mean penalties, delays at build-up or a rejected design, so plan the stall design around the manual's deadlines.
- Common problems include stalls above the height limit, unfinished walls facing neighbours, non-fire-retardant materials and power loads that were never ordered.
- Your stall contractor should handle most of the paperwork, but the exhibitor is responsible for booking, payments and meeting the organiser's deadlines.
A good stall design is only half of the job. Before your stall can be built in the hall, the organiser usually has to approve it. Miss a deadline or overlook a rule and you can face penalties, a delayed build-up or, at worst, changes to your stall on site.
This guide explains how the exhibition stall approval process typically works at Indian trade fairs, what the exhibitor manual contains, which documents organisers ask for and how to plan your timeline so approvals never become a last-minute problem.
Rules differ from show to show and venue to venue. Use this guide to know what to look for, and always follow the exhibitor manual for your specific exhibition.
Why Organisers Approve Stalls
Organisers are responsible for the safety of everyone in the hall and for a fair, orderly show. Approvals help them check that:
- Stalls are structurally safe and stay within the booked area and height limits.
- Materials and electrical work meet fire and safety requirements.
- Power loads are planned, so the hall supply is not overloaded.
- Neighbouring exhibitors are not blocked or faced with unfinished walls.
- Contractors working in the hall are identified and accountable.
Start With the Exhibitor Manual
The exhibitor manual (sometimes called the exhibitor handbook or technical manual) is sent after you book space or is available on the event website. It is the most important document for your stall. Read it before you brief your designer, not after the design is approved.
A typical manual covers:
- Key deadlines for drawings, contractor registration, power orders, fascia names and services.
- Build-up and dismantling schedule, including timings and access for vehicles.
- Stall construction rules, such as height limits, setbacks from the plot boundary and rules for open sides.
- Material and fire safety rules, for example requirements for fire-retardant materials and fire extinguishers.
- Electrical rules, how to order power, charges and who may make connections.
- Rigging and hanging rules for banners or structures suspended from the hall roof.
- Contractor requirements, including registration, deposits, badges and insurance.
- Order forms for extra furniture, AV, cleaning, security and other services.
Documents Organisers Usually Ask For
For bare-space stalls, the most common submissions are:
| Document | What it shows | Who prepares it |
|---|---|---|
| Stall plan (top view) | Layout, dimensions, open sides, entrances | Stall designer |
| Elevations and 3D views | Heights, fascia, branding, wall finishes | Stall designer |
| Structural details | Load-bearing elements, double-decker or tall structures | Fabricator or structural engineer |
| Electrical layout and load | Light points, sockets, AV, total load in kW | Fabricator |
| Contractor registration | Company details, contact person, team list | Fabricator |
| Power order | Required load and connection type | Exhibitor, often with fabricator's input |
| Rigging request | Hanging points and weights, if allowed | Designer or fabricator, via approved rigger |
Some shows also ask for undertakings, insurance documents or a refundable security deposit from the contractor to cover damage or debris left after dismantling.
Common Rules That Affect Stall Design
The rules below appear in many exhibitor manuals. The exact limits vary, so check your manual for numbers.
Height Limits
Most shows set a maximum stall height, sometimes with different limits for walls on the boundary, the centre of the stall and island plots. Logo towers and hanging banners may have their own rules.
Walls Facing Neighbours
If your stall wall faces a neighbouring stall, many manuals require the back to be finished neatly, often in plain white with no branding. Plan and budget for this.
Open Sides and Setbacks
Corner and island stalls may need to keep a share of each open side unobstructed. Some shows also require walls to be set back from the aisle.
Fire Safety
Requirements often include fire-retardant materials or treatment, proper electrical wiring and fire extinguishers on stalls above a certain size. Highly flammable decorations may be restricted.
Floor Protection
Drilling, painting or fixing directly to the hall floor is generally not allowed. Platforms and flooring are laid on top of protective layers.
Double-Decker Stalls
Two-level stalls usually need separate approval, structural drawings and sometimes a certificate from a qualified engineer, with earlier deadlines than standard stalls.
Typical Approval Timeline
| Weeks before the show | Step |
|---|---|
| 10–12 | Book space, receive the exhibitor manual, note deadlines |
| 8–10 | Brief your designer with the manual's rules |
| 6–8 | Approve the 3D design; fabricator prepares drawings |
| 5–6 | Submit drawings, contractor registration and power order |
| 3–4 | Organiser approval; make any changes requested |
| 2–3 | Fabrication, graphics printing and quality checks |
| Build-up | Contractor badges, power connection, final inspection |
Large, double-decker or heavy machinery stalls need more time. Late submissions often carry penalty charges or are not accepted.
Common Approval Mistakes
- Designing before reading the manual, which leads to stalls that exceed height limits or block open sides.
- Forgetting to order power, or ordering too little for LED walls, machines and lighting.
- Unfinished walls facing neighbours, which organisers may ask you to cover on site.
- Unregistered contractors, who may not be allowed into the hall during build-up.
- Last-minute design changes after approval, which can need resubmission.
- Ignoring dismantling rules, leading to deductions from deposits for debris or late removal.
Build-Up and Dismantling Rules to Plan For
Approval of the drawings is not the end of the process. Build-up and dismantling days have their own rules, and they affect both your contractor's schedule and your budget.
- Fixed working hours. Many venues allow work only within set hours on build-up days. Night work, if allowed at all, may need permission and extra charges.
- Badges and entry passes. Contractor staff usually need passes, issued only after registration. Send the team list on time so nobody waits at the gate.
- Vehicle entry and unloading. Large shows may give each contractor an unloading slot. Missing it can mean waiting for hours with a loaded truck.
- Power connection timing. Permanent power is often connected only on the last build-up day. Plan lighting tests and AV checks for that window.
- Final inspection. Some organisers inspect stalls before opening for safety, fire extinguishers and compliance with the approved drawings.
- Dismantling window. Stalls must be cleared within a fixed period after the show closes. Debris left behind or late removal can be charged against the contractor's deposit.
- Security of exhibits. Remove valuable products and equipment as soon as the show ends; dismantling time is when most losses happen.
Pre-Submission Checklist
Before you send drawings to the organiser, check that:
- Stall dimensions match the booked plot exactly, including open sides.
- All heights, including logo towers and hanging elements, are within the limits.
- Walls facing neighbours are shown with a neat, plain finish.
- Materials meet the manual's fire safety requirements.
- The electrical layout lists every light, socket, screen and machine, with a total load that matches the power order.
- Double-decker or rigging elements have the separate approvals they need.
- Contractor registration, team list and deposit are submitted.
- You have kept copies of every submission and the organiser's confirmation.
Who Is Responsible for What?
| Task | Exhibitor | Stall contractor |
|---|---|---|
| Booking space and paying the organiser | Yes | No |
| Sharing the exhibitor manual and deadlines | Yes | Should follow up |
| Stall design, drawings and electrical layout | Approves | Prepares |
| Contractor registration and deposit | Confirms | Usually handles |
| Power order | Often places the order | Advises on load |
| On-site safety and compliance | Overall responsibility | Executes |
A good fabricator will take care of most of the technical paperwork. Ask about this before you hire. Our list of questions to ask an exhibition stall fabricator covers approvals and other important checks.
How a 3D Design Helps With Approvals
A detailed 3D design with dimensions makes the approval process smoother. The organiser can see heights, open sides and branding clearly, and you can check them against the manual before submission. Our guides on what to check in a 3D stall design before approval and the checklist before fabrication are useful at this stage.
Frequently Asked Questions
Do shell scheme stalls need approval?
Usually less than bare-space stalls. You may still need to submit fascia text, graphics fixing methods and any extra power or furniture orders. Check the exhibitor manual.
How early should I submit stall drawings?
Follow the deadline in the exhibitor manual. As a guide, many shows ask for drawings four to six weeks before build-up, and earlier for double-decker or special structures.
What happens if my stall is not approved?
The organiser will usually ask for changes, such as reducing height or finishing a wall. Making the changes before fabrication costs far less than altering a built stall on site.
Who orders electricity for the stall?
The exhibitor usually orders and pays for power through the organiser, based on the load calculated by the stall contractor. Connections are typically made by the organiser's appointed electrical contractor.
Can my stall contractor handle all approvals?
A professional contractor can prepare and submit most technical documents, but the exhibitor remains responsible for booking, payments and meeting the organiser's deadlines.
Let Us Handle the Technical Side
Connectbase Communications has designed and built more than 2,000 exhibition stalls since 2009. Our team prepares 3D designs, drawings and electrical layouts to suit the exhibitor manual, and handles fabrication, installation and dismantling with our own crew.
Share your show and exhibitor manual with us, and we will plan your stall around the rules from the start. Learn about our stall design and fabrication services, or contact us for a stall design quotation.